Resources
Install Checklist
Installation checklists that help teams fit cutting cells and tooling in the right order, with fewer missed steps.
How the Install Checklist supports a real install week
The Install Checklist page gives teams a workable fitting order for cutting cells and shop tooling. It helps site crews tick off the key checks before power-up, so missed steps do not become machine faults later in the job.
An install checklist starts with the machine position, available power, and the tooling that must be fitted before first motion. On South African sites, teams often have to account for dust build-up, coastal air, and stoppages from load-shedding before commissioning can begin. The sheet sets those checks in order so the crew can verify services, guards, and cut settings before the cell is energised.
Keep a photo record from the first unpacking stage through to final guard fitment. That record helps installers confirm cable routes, anchor points, and sensor positions if work pauses between shifts. A printed copy near the machine also gives the next team a fixed reference for lubrication, blade rotation, and safety checks.
Power-up order and fitment points
The page lays out a fitting sequence for cutting cells and shop tooling, from base placement to first test cut. It gives supervisors a working list for air lines, extraction, fasteners, interlocks, and datum checks. Clear naming on the checklist helps match each step to the correct toolholder, blade set, or consumable.
Use the Install Checklist alongside the linked references for Applications and Edgework when the job includes more than one cut type. Before the crate is closed or the machine is handed over, compare the checklist against the tooling list and dispatch paperwork so nothing is omitted. Writing in? Include the floor space and power supply at the install point in the contact form.
- Machine position checked before anchoring
- Guard and sensor checks logged
Site conditions that affect commissioning
Many installations happen in running workshops where access is tight and production equipment cannot simply be moved aside. The checklist therefore covers service clearances, lifting space, and the order for bringing components into position without blocking the line. It also helps teams note older slabs, uneven mounting points, or restricted extraction routes before fixings are drilled.
Near the coast, moisture and grit can alter cleaning intervals and the condition of exposed metal parts during install week. Inland workshops tend to battle fine dust, which matters for linear guides, sensors, and cabinet seals before start-up checks are signed off. Where power cuts are common, the list also helps crews record which settings must be rechecked after an interruption.
Operated by Astros Marketing (Pty) Ltd from 2 Makro Place, Sunnyrock 1401.
What to note before handover
Record the cell name, tooling set, available voltage, air supply details, and any deviation found during fitting. Add photos of the mounted tooling, the guarding arrangement, and the first sample cut if one has been run. Those notes make later fault-finding easier when a part is moved, replaced, or re-aligned.
Store the completed checklist with the project file and the relevant resource page for that machine. It gives buyers, fitters, and maintenance staff one record of what was installed, what was verified, and what still needed attention at handover. On busy sites, that written trail is often the only way to distinguish a missed install step from a later machine fault.